R-02 · Tier 1 · Payment

Cross-Project Offset

Contractor may apply money owed on one project to alleged breaches on another project.

What MillworkShield looks for

This is the business risk behind the clause.

Risk

The GC can weaponize earned funds from one job against disputes on another.

Cleaner ask

Strike entirely; each project's funds should stand alone.

Reference context

Not in AIA A401 or ConsensusDocs 750; custom GC-favoring add.

Search nearby wording

condition precedentpayment by ownerif contractor is paidpay when paid

Related guide

Pay-if-paid: the clause that makes your shop finance the owner

Can we revise the payment clause so approved work is paid within a fixed window and owner nonpayment that is unrelated to our scope does not become our shop's credit risk?