R-03 · Tier 1 · Notice and waiver
Sub Cure Window < 72 Hours
Default or defective-work cure period is 24, 48, or 72 hours.
What MillworkShield looks for
This is the business risk behind the clause.
Risk
Hair-trigger default tool that can manufacture breach, backcharge, or supplementation claims.
Cleaner ask
Move cure period to at least seven business days, with diligent-cure extension.
Reference context
AIA A201 §2.4 is 10 days; ConsensusDocs 750 is typically 7 days.
Search nearby wording
backchargesupplementdeductcure
Related guide
Backcharges: how cleanup costs become your problem
Can we add written notice, a reasonable cure period, and backup documentation before any backcharge is deducted from our payment?