R-10 · Tier 2 · Notice and waiver
Delay Notice < 7 Days from Condition Onset
Delay notice is due within 24, 48, or 72 hours from condition onset.
What MillworkShield looks for
This is the business risk behind the clause.
Risk
Minor-looking events that compound later become late-notice waiver fights.
Cleaner ask
Use seven business days from when the impact is reasonably knowable.
Reference context
AIA A201 §15.1.3 is 21 days; ConsensusDocs is typically 14 days.
Search nearby wording
backchargesupplementdeductcure
Related guide
Backcharges: how cleanup costs become your problem
Can we add written notice, a reasonable cure period, and backup documentation before any backcharge is deducted from our payment?