R-13 · Tier 2 · Delay damages

No-Damages-for-Delay + Sole-Remedy Time Extension

No-damages-for-delay clause combines with time-extension-only remedy.

What MillworkShield looks for

This is the business risk behind the clause.

Risk

Every money claim for delay converts to time only, forcing the sub to absorb delay costs.

Cleaner ask

Add carve-outs for GC/Owner-caused delay, directed acceleration, out-of-sequence work, and long suspensions.

Reference context

AIA and ConsensusDocs allow delay damages with notice; absolute NDFD is GC-favoring.

Search nearby wording

liquidated damagestime is of the essenceno damages for delaysole remedy

Related guide

Delay damages: do not carry the whole schedule on your back

Can we limit delay exposure to delays actually caused by our shop, add a reasonable cap, and preserve time extensions for late access, approvals, changes, and predecessor delays?