No Sub Stop-Work Right for Non-Payment

Payment and suspension terms omit a sub stop-work right for non-payment.

What MillworkShield looks for

This is the business risk behind the clause.

Risk

Sub must keep working without a contractual suspension lever and invoke statute separately.

Cleaner ask

Add suspension right after unpaid undisputed amounts plus demob/remob recovery.

Reference context

AIA A401 §4.7 grants stop-work rights; TX Property Code §28.009 supplies a statutory path.

Search nearby wording

condition precedentpayment by ownerif contractor is paidpay when paid

Related guide

Pay-if-paid: the clause that makes your shop finance the owner

Can we revise the payment clause so approved work is paid within a fixed window and owner nonpayment that is unrelated to our scope does not become our shop's credit risk?