R-18 · Tier 2 · Termination and suspension
No Sub Termination-for-Cause + No Demob Recovery
GC has convenience termination rights without parallel sub termination/cost recovery.
What MillworkShield looks for
This is the business risk behind the clause.
Risk
GC can terminate at will while sub absorbs demobilization and has no escape for GC default.
Cleaner ask
Add sub termination for cause and demob/material cost recovery on convenience termination.
Reference context
AIA A401 §4.7.2 grants sub termination rights and cost recovery.
Search nearby wording
termination for conveniencewithout causeonly work performedno lost profits
Related guide
Termination for convenience: when the GC can walk away from your sunk costs
Can we revise convenience termination so the shop is paid for performed work, custom materials, committed costs, demobilization, and reasonable overhead and profit?