R-24 · Tier 4 · Delay damages

Overtime / Acceleration at Sub's Cost Absent CO

Schedule compliance costs, including overtime, are included absent a change order.

What MillworkShield looks for

This is the business risk behind the clause.

Risk

Sub absorbs acceleration cost unless directives are papered as COs in real time.

Cleaner ask

No standard redline; require written CO before acceleration.

Reference context

Generally standard; the practical remedy is contemporaneous CO discipline.

Search nearby wording

liquidated damagestime is of the essenceno damages for delaysole remedy

Related guide

Delay damages: do not carry the whole schedule on your back

Can we limit delay exposure to delays actually caused by our shop, add a reasonable cap, and preserve time extensions for late access, approvals, changes, and predecessor delays?