R-24 · Tier 4 · Delay damages
Overtime / Acceleration at Sub's Cost Absent CO
Schedule compliance costs, including overtime, are included absent a change order.
What MillworkShield looks for
This is the business risk behind the clause.
Risk
Sub absorbs acceleration cost unless directives are papered as COs in real time.
Cleaner ask
No standard redline; require written CO before acceleration.
Reference context
Generally standard; the practical remedy is contemporaneous CO discipline.
Search nearby wording
liquidated damagestime is of the essenceno damages for delaysole remedy
Related guide
Delay damages: do not carry the whole schedule on your back
Can we limit delay exposure to delays actually caused by our shop, add a reasonable cap, and preserve time extensions for late access, approvals, changes, and predecessor delays?