R-26 · Tier 2 · Trade-specific scope
Risk of Loss on Custom-Fabricated Millwork Pre-Installation
Risk of loss passes only on installation, not delivery or stored-material payment.
What MillworkShield looks for
This is the business risk behind the clause.
Risk
Custom millwork value accumulates before installation and can be uninsured against theft or damage.
Cleaner ask
Transfer risk on delivery or stored-material payment and require Builder's Risk coverage.
Reference context
UCC §2-509 and commercial practice support transfer on delivery/acceptance or stored-material payment.
Search nearby wording
complete scopereasonably inferableincidental workall documents
Related guide
Scope gaps: the sentence that makes you own work you never priced
Can we incorporate our proposal, exclusions, and assumptions, and clarify that drawing gaps, site-condition changes, and work by others are handled through change orders?