R-27 · Tier 2 · Trade-specific scope

Shop Drawing Approval Without Turnaround Timeline

Shop drawing review is required but has no return deadline.

What MillworkShield looks for

This is the business risk behind the clause.

Risk

Late approvals delay fabrication, which delays installation and exposes the sub to schedule liability.

Cleaner ask

Require 14-day initial return and 7-day resubmittal return.

Reference context

AIA A201 §3.10 contemplates timely review.

Search nearby wording

complete scopereasonably inferableincidental workall documents

Related guide

Scope gaps: the sentence that makes you own work you never priced

Can we incorporate our proposal, exclusions, and assumptions, and clarify that drawing gaps, site-condition changes, and work by others are handled through change orders?