Change order / extra work ask language for the GC.

Extra work is normal in commercial construction. The contract decides whether extra work becomes paid work.

Direct ask

Change order / extra work

Copy-paste ask

Can we add a field-friendly change path so written direction from the GC team preserves pricing and schedule rights while the formal change order catches up?

Use when the contract says

No extra or changed work will be compensated unless authorized by a fully executed change order before the work starts.

Ask the GC to move toward

Written field direction or email approval preserves Subcontractor's right to time and compensation while formal change-order paperwork is completed.

Escalate if

Escalate if the job is fast-moving, changes are likely, or the clause requires work to proceed before price, scope, or time impact is resolved.

Generate from the document

MillworkShield can tailor this ask to the actual contract wording.

Upload the subcontract, mark this issue Fight, and copy the GC-ready response.