Payment paperwork
Lien waiver / payment bond claim waiver ask language for the GC.
Lien waiver language can look like routine payment paperwork. The wrong form can give away rights before the check is good.
Lien waiver / payment bond claim waiver
Can we use conditional waivers until funds clear and limit each waiver to the exact payment amount, through-date, and work actually being paid?
Subcontractor waives lien rights and will execute an unconditional waiver before payment is released.
Subcontractor will provide conditional waivers before payment and unconditional waivers only after corresponding good funds are received.
Use counsel if a waiver releases unpaid change orders, retainage, delay claims, or all project rights before money is in the account.